Spain’s Renewable Curtailment Bill Hits €140 Million as Solar Pipeline Swells

Green Energy News
17.11.2026

Spain’s grid is absorbing the financial fallout from mounting renewable curtailment, with Wood Mackenzie putting market losses at €140 million since a large-scale disconnection event in April 2025. Unabsorbed generation has already equalled 4 percent of available renewable energy supply this year, and analysts expect conditions to worsen.

The grid management picture involves two distinct pressures: gas-fired capacity is being dispatched to substitute for curtailed solar output, while wind farms are separately taken offline to preserve system stability. At certain nodes in central-eastern and south-western Spain, renewable output is already being cut by more than 25 percent.

Data source: Wood Mackenzie
Data source: Wood Mackenzie

The strain is set to grow. Nearly 10 GW of industrial solar is scheduled to connect in Q4 2026 and through 2027–2028. Without inverter upgrades across the existing fleet — around 7 GW of solar and 26 GW of wind require voltage-control modifications — curtailment could increase by a further 18 percent over two years, pushing lost generation to 6.5 TWh by 2028 against 1.3 TWh in 2023.

A Wood Mackenzie analyst notes that the 2027 outlook depends almost entirely on how quickly owners retrofit the existing 35 GW fleet, work that requires no additional capital outlay for inverter adjustments. Physical grid expansion averages seven years, so batteries and rising electricity demand represent the realistic short-term remedies. Over 40 GW of storage is in development, with 10 GW forecast to be operational by the end of the decade.