Google Bets $500 Million on Superhot Geothermal to Power Oregon Data Centers
Google has signed a power purchase agreement with Quaise Energy for superhot geothermal electricity, becoming the first large commercial buyer of the technology and moving it closer to industrial scale after years of demonstration-stage development.
The contract is valued at more than $500 million and covers the Obsidian project, located near Newberry Volcano in Oregon. The plant is designed to deliver stable, carbon-free electricity to Google data centers in The Dalles, with 50 MW of capacity potentially coming online as early as 2030. Total two-phase construction costs are estimated at $350 million.
Scaling the technology depends on a fundamental change in how the wells are drilled. The first phase uses conventional drilling methods; the second introduces millimeter-wave technology that destroys rock through energy rather than physical contact. This would enable wells reaching up to 65,000 feet (roughly 20 kilometres), where rock temperatures exceed 500 °C — heat that renders standard drill bits unusable.
A Quaise representative said such superhot wells could generate up to ten times more energy per installation than conventional geothermal setups, making the approach economically viable where it previously was not.
Work is already under way: the company reports that 118 metres of granite have been penetrated at a test site in Texas, with the team now targeting the one-kilometre depth milestone.
Source: Utility Dive