SSE Discloses Turbine Repairs at Dogger Bank A as CfD Mechanism Start Shifts to July 2027

Green Energy News
23.11.2026

British energy company SSE has disclosed that several dozen of the 13 MW Haliade-X turbines installed at the Dogger Bank A offshore wind farm in the North Sea require repair work and component replacement before the project reaches full design capacity, industry publication reNews reports. SSE chief executive Martin Pibworth revealed the technical issues to analysts during this week’s financial results call.

GE Vernova is carrying out the remediation work alongside operator SSE. Some of the affected units need repairs, while others require replacement of individual components. Pibworth said approximately 150 turbines have been installed across all phases of Dogger Bank, with 100 already generating power. Capacity from the Dogger Bank A phase is expected to be largely available by the end of the first quarter of 2027.

In a separate project timeline development, state body Low Carbon Contracts Company has moved the launch of the CfD mechanism under the AR3 round for the first 300 MW phase from late November to 31 July 2027.

Pibworth described the company’s ultimate goal as receiving a project and assets with very high reliability and a quality commissioning process, adding that work would continue with that objective in mind. The Dogger Bank consortium also includes Equinor and Vårgrønn.