France’s energy regulator CRE has issued its assessment of the proposed rules for the opening round of the PPE3 Neutre competitive scheme, which is set to accept applications from January 2027. The contest will allocate 500 MW across solar, onshore wind, and hydropower installations.

The most consequential design change is a sharp increase in the scoring weight of the price criterion — up from 70% to 95% of the total evaluation. Carbon footprint and environmental factors, which previously accounted for the remaining 30%, now carry almost no scoring weight. A bid price ceiling of €100 per MWh applies. The revised framework also replaces the previous pricing mechanism with an unweighted base-price reference known as M0.

CRE itself flags economic concerns with the new approach. An unweighted M0 reference could push developers toward higher risk premiums, shorter financing tenors, costlier debt, and lower leverage ratios. Aggregation contracts — which typically run one to three years — add a further layer of uncertainty over long-term project costs, since they are considerably shorter than standard difference contracts.

Industry reaction has been skeptical. The French renewable energy association SER argued that the 500 MW envelope falls well short of market needs, noting that solar developers alone had requested 1.5 GW. Lack of forward visibility on future tender volumes also continues to deter investment planning.

Some concessions are on offer for hybrid projects: developers would not be required to hold an administrative permit for a battery storage component at the point of bid submission. The minimum project size for solar has also been raised from 500 kW to 1 MW.