Greece Selects 4.7 GW of Battery Storage Projects From Record Pipeline
Greece has approved connection terms for 4.7 gigawatts of battery energy storage out of a record pool of 831 applications totalling more than 12.3 GW, the Ministry of Environment and Energy announced. The selection marks a decisive push toward market-driven storage deployment after the country’s first state-backed projects — from an auctioned 900 MW tranche — began operating earlier this year.
Of the submissions, 10.5 GW targeted the transmission grid and 1.8 GW the distribution network. Following technical assessment, authorities approved 6,366 MW (including reserve slots) on the transmission side and 1,403 MW on the distribution side, yielding the combined 4,700 MW that will advance to formal connection terms.
Several large developers secured significant transmission-grid allocations:
- Public Power Corporation — 470 MW across five projects, four of them located in coal-mining regions including the Florina area
- Rokas — 220 MW
- Terna Energy — 197.5 MW
- HELLENiQ Renewables — 50 MW
Hundreds of smaller investments were placed on the list managed by distribution operator HEDNO.
The government’s stated target is to have between 5 and 7 GW of storage in operation by 2028. That capacity is expected to ease forced curtailment of renewable generation, lift daytime wholesale electricity prices in support of solar producers, and ultimately reduce overall costs for consumers. The next stage requires the two grid operators to issue individual connection terms ranked by project category.